iprnagaland[at]gmail[dot]com (0370) 2271492 (Office)

Department of Power, Office of Executive Engineer Transmission Division has informed all concerned that Vegetation Clearance for 132kV and 66kV Transmission Lines under Transmission Division Mokokchung is scheduled from 23rd Oct 2023 to 18,b November 2023. In this regard, there will be total shutdown of power from 08:00 AM to 4:00 PM daily in order to facilitate smooth execution of the works. This exercise is necessitated with the aim to provide stable power supply and avoid unwarranted disruption of supply.

The department appeals to all public in the affected areas to extend cooperation and bear the inconvenience during the shutdown period.

SI. No

Schedule Date

Feeders

Affected area under Shut Down

1

23rd - 28th Oct. 2023

66kV Mokokchung- Zunheboto Transmission Line

Zunheboto District.

2

30th Oct. - 3rd Nov. 2023

132kV Mokokchung- Doyang Transmission Line

 

3

06th- 11th  Nov. 2023

66kV Mokokchung-Tuli

66 kV Tuli-N/Mora

66kV N/Mora-Tizit

66kV Tizit-Mon Transmission

Line

Changtongya Sub-Div, Tuli Sub-Div, Longleng & Mon District.

4

13th - 18th Nov. 2023

132kV Mokokchung-Mariani Transmission Line

 

 

(DIPR)