Chairman of the Public Accounts Committee (PAC), Nagaland Legislative Assembly, Mhathung Yanthan, MLA, with Committee Member, Tongpang Ozukum and others during the on-the-spot verification of the project “Development of Tribal Circuit at Peren, on 14th November 2026. (DPRO Peren)
Chairman of the Public Accounts Committee (PAC), Nagaland Legislative Assembly, Mhathung Yanthan, MLA, with Committee Member, Tongpang Ozukum and others during the on-the-spot verification of the project “Development of Tribal Circuit at Peren, on 14th November 2026. (DPRO Peren)

Photo News · Peren

The Chairman of the Public Accounts Committee (PAC) of the Nagaland Legislative Assembly, Mhathung Yanthan, MLA, along with Committee Member, Tongpang Ozukum, conducted an on-the-spot verification of the project “Development of Tribal Circuit Peren, Nagaland” under the Swadesh Darshan Scheme at New Peren on 14th November 2026.

The project was approved in November 2015 by the Ministry of Tourism, Government of India, comprising of 43 project components which were split into 2.0 zones namely Accomodation Zone (log huts, Tourist facilitation centre, cafeteria, rejuvenation centre etc) and Recreational Zone (Open-air-theatre, 16 tribal huts, multipurpose hall and helipad). Plantation of Biological fencing around the campus and roadside, Solid Waste Management System and Campus illumination with solar energy & Directional Signages were also part of the activities undertaken within the 43 project component.

The on-the-spot verification was undertaken in connection with the examination of the Controller and Auditor General (C&AG) of India Report for the year 2022–2023 on Social (including Local Governments Audit), Economic, General and Revenue Sectors. The decision to conduct the spot verification was taken following the oral evidence meeting held on 28th October 2026 with the Departmental representative at C Chongsen Committee Room, Assembly Secretariat.

During the visit, the Committee inspected the project site and took stock of the progress and implementation of the project. It also reviewed the execution of works and assessed the utilisation of funds in relation to the objectives and intended outcomes of the project. The officials also briefed the Committee on the present status of the project and apprised it of the various aspects of its execution.

With regard to the provision of water supply, road connectivity and electricity at the project site, the Committee recommended that the concerned departments take necessary action to address these requirements at the earliest. The contractors also assured the Committee that the pending works would be completed once the proper water supply, road connectivity and electricity facilities are provided by the concerned departments.