ADC Kohima, N. Bhavani Sri, IAS has informed all concerned that jungle clearance and maintenance programme of 132kV, 66kV & 33kV lines is scheduled from 1st October 2021 to 14th November 2021 from 8 am to 3 pm in an effort to avoid disruption and facilitate stable power supply.

While the Department of Power shall try to minimize the total shutdown, there will be intermittent disruption of power supply in some pockets during the activity which is unavoidable. Therefore all consumers and public are requested to bear the inconvenience caused.

 

SI

Schedule Date

Feeder

Affected Area to be under Total Shutdown

1

1st Oct 21 to 2nd Oct 21

132 kV Kohima to Dimapur

 

2

9th Oct 21 to 10th Oct 21

132kV Doyang to Sanis

 

3

11th Oct 21 to 12th Oct 21

132kV Wokha toSanis

 

4

13th Oct 21 to 16th Oct 21

132kV Kohima to Wokha

 

5

18th Oct 21 to 20th Oct 21

132kV Kohima to Karong

 

6

22nd Oct 21 to 26th Oct 21

66kV Kiphire to Tuensang

Phek, Kiphire district and Likimro HEP

7

27th Oct 21 to 30th Oct 21

66kV Kiphire to LHEP

Likimro HEP

8

1st Nov 21 to 5th Nov 21

132kV Kiphire to Meluri

Phek District

9

6th Nov 21 to 14th Nov 21

132kV Meluri to Kohima

 

9

4th Oct 21 to 11th Oct 21

33kV Botsa

Northern Angami Area Kohima

10

12th Oct to 13th Oct 21

33kV Jakhama

Southern Angami Area Kohima

11

14th Oct to 16th Oct 21

33kV KRM-1

 

12

 18th Oct 21

33kV KRM-2

 

13

19th Oct 21 to 23rd Oct 21

33kV Lalmati/AP-1

Zubza and Lalmati area

14

25th Oct 21 to 27th Oct 21

33kV Chakhabama

Chakhabama & Chozuba area

 

(Siizo Kikhi IA Kohima)